# AI data center power demand: AIxEnergy Weekly Media Benchmark, 2026-W46

Source: AIxEnergy (aixenergy.io/benchmarks). License: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/)

Data as of November 15, 2026. Model ELL-2.2.0. Updated every Monday.

- Latest release: https://www.aixenergy.io/benchmarks/
- Permalink for this week (figures fixed for the week): https://www.aixenergy.io/benchmarks-2026-w46/

## Key findings

- U.S. ISO large-load queues hold 175.40 GW of data center and AI requests (467 positions, 9 grid operators), +18.17 GW since the October 1, 2026 snapshot.
- AIxEnergy's ELL-2.2.0 model expects 43.85 GW of that load to be built; 75.0% is speculative or blocked.
- The 15 largest sponsors have a 108.42 GW pipeline across 568 campuses, with $654.56bn of capital disclosed in filings; the modeled build-out cost is $1,119.91bn (AIxEnergy estimate).
- 20 verified campus capital filings total $153.77bn for 17,549 MW of disclosed load.
- AIxEnergy tracks 112 local pushback flashpoints and 987 restrictive local policies on data centers.
- 18,702 MW of nuclear, SMR and geothermal supply is contracted to data centers (37 nuclear plants, 14 geothermal pairings).
- Wholesale power in 24 AI data center pricing zones averaged $49.98/MWh in 2025, weighted by zonal load (simple average $49.33/MWh).

## Headline numbers

- Large-load queue, gross: 175.40 GW. Capacity requested in U.S. ISO queues. [https://www.aixenergy.io/benchmarks-2026-w46/#n-gross-gw]
- Expected to be built: 43.85 GW. ELL-2.2.0 estimate of the queue that reaches service. [https://www.aixenergy.io/benchmarks-2026-w46/#n-realized-gw]
- Phantom or blocked share: 75.0%. Requested capacity the model treats as speculative or blocked. [https://www.aixenergy.io/benchmarks-2026-w46/#n-phantom-pct]
- Top-15 sponsor pipeline: 108.42 GW. Planned and active load at the 15 largest sponsors' campuses. [https://www.aixenergy.io/benchmarks-2026-w46/#n-pipeline-gw]
- Disclosed capital, top 15: $654.56bn. Capital stated in company filings. [https://www.aixenergy.io/benchmarks-2026-w46/#n-disclosed-capital-b]
- Modeled build-out cost, top 15: $1,119.91bn. Pipeline GW × assumed cost per MW; not company-disclosed. [https://www.aixenergy.io/benchmarks-2026-w46/#n-modeled-buildout-cost-b]
- Verified capital filings: $153.77bn. Campus capital commitments verified against filings. [https://www.aixenergy.io/benchmarks-2026-w46/#n-verified-filings-usd-m]
- Queue at named utilities: 89.60 GW. Share of the Table 1 queue held by named utilities. [https://www.aixenergy.io/benchmarks-2026-w46/#n-gross-gw]
- Load at top-25 corridors: 50.83 GW. Requested load at the 25 named corridors. [https://www.aixenergy.io/benchmarks-2026-w46/#n-stacked-gw]
- Local pushback flashpoints: 112 jurisdictions. Places opposing, pausing or restricting projects. [https://www.aixenergy.io/benchmarks-2026-w46/#n-pushback-hubs-db-total]
- Restrictive local policies: 987 rules. Moratoria, ballot bans and zoning constraints. [https://www.aixenergy.io/benchmarks-2026-w46/#n-policy-regimes-db-total]
- Nuclear, SMR and geothermal contracted: 18,702 MW. Contracted supply for data centers; planned MW excluded. [https://www.aixenergy.io/benchmarks-2026-w46/#n-total-contracted-clean-firm-mw]
- Wholesale price, 24 AI hub zones: $49.98/MWh. 2025, weighted by zonal load. [https://www.aixenergy.io/benchmarks-2026-w46/#n-load-weighted-avg-lmp-2025-usd-mwh]

## Questions and answers

### How much power do AI data centers need?

As of November 15, 2026, large-load interconnection queues hold 175.40 GW of data center and AI requests. AIxEnergy's ELL-2.2.0 model expects 43.85 GW to be built. These are grid requests, not electricity consumed.

### What is a data center interconnection queue?

A grid operator's list of projects waiting to connect. Developers file in several places and many requests are never built; AIxEnergy estimates 75.0% of queued data center capacity is speculative or blocked.

### Are data centers raising electricity prices?

Wholesale power in the 24 pricing zones with the most data center development averaged $49.98/MWh in 2025, weighted by zonal load. The benchmark reports prices; it does not attribute changes to data centers alone.

### Which companies have the most data center power in the pipeline?

The 15 largest sponsors account for 108.42 GW. Largest this week: Oracle / OpenAI (Stargate) (19.2 GW), Meta Platforms (11.7 GW), Microsoft (11.1 GW).

### How many places are pushing back on data centers?

AIxEnergy tracks 112 local jurisdictions where residents or officials have opposed, paused or restricted projects, and 987 restrictive local policies.

### How often is this updated, and can I reuse it?

Every Monday, US Eastern time. Excel, CSV and JSON files are free under CC BY 4.0; credit “Source: AIxEnergy (aixenergy.io/benchmarks)” and name the release week (2026-W46).

## Files

- Full workbook (Excel): https://storage.ghost.io/c/e3/c9/e3c9e740-20f7-4e9c-9a31-131fc1166819/content/files/2026/11/AIxEnergy_Weekly_Media_Benchmark_2026_W46-3.xlsx
- All files (ZIP): https://storage.ghost.io/c/e3/c9/e3c9e740-20f7-4e9c-9a31-131fc1166819/content/files/2026/11/AIxEnergy_Weekly_Media_Benchmark_2026_W46_All_Files-5.zip
- One-page brief (PDF): https://storage.ghost.io/c/e3/c9/e3c9e740-20f7-4e9c-9a31-131fc1166819/content/files/2026/11/AIxEnergy_Weekly_Media_Benchmark_2026-W46_Brief-8.pdf

Modeled figures are ELL-2.2.0 model outputs or AIxEnergy estimates. Methodology: https://www.aixenergy.io/benchmarks/#methodology